Alert 10/12: Bell Street closed between 5th and 6th Avenues for up to 3 weeks

Map of the full Bell Street project.Heads up! Work is underway to complete the Bell St bike lane and install new signals between 5th and 6th Avenues. This means the street will be closed 24/7 for up to three weeks, according to SDOT:

The Bell St Protected Bike Lane project will resume construction next Monday, 10/12. Our remaining work includes:

  • Install new traffic signals infrastructure at west corner of 6th Ave and Bell St
  • Construct ADA compliant curb ramps at all four corners of 6th Ave and Bell St
  • Install new low landscaping in curbed barrier between protected bike lane and parking lane, between 5th Ave and Denny Way

Please note that our work will require temporary full closure of Bell St between 5th Ave and 6th Ave to vehicular traffic (except for emergency vehicles) for up to 3 weeks, beginning next Monday, 10/12. The closure will be in place 24/7 until the signal installation is complete. Due to the restricted roadway space and nearby construction work, full closure of Bell St between 5th and 6th Ave is the only feasible option to safely install the new signal. We apologize in advance for any inconvenience this may cause. During this closure, please expect delays when traveling in and around the area and follow signs for detour.


— Advertisement —

If you have any questions or concerns, please feel free to contact us at [email protected] or by phone at 206-900-8760.

Thank you for your patience as we install right-of-way improvements in your neighborhood.


About the author:


Related posts:

— Advertisement —

Join the Seattle Bike Blog Supporters

As a supporter, you help power independent bike news in the Seattle area. Please consider supporting the site financially starting at $5 per month:


Latest stories

Bike Events Calendar

May
30
Thu
7:15 pm Point83 @ Westlake Park
Point83 @ Westlake Park
May 30 @ 7:15 pm
Point83 @ Westlake Park
Meet up in the center of the park at 7ish. Leave at 730. Every Thursday from now until forever rain or shine. Bikes, beers, illegal firepits, nachos, bottlerockets, timetraveling, lollygagging, mechanicals, good times.ShareMastodonTwitterFacebookRedditEmail
Jun
1
Sat
9:00 am First Saturday Neighborhood Clea…
First Saturday Neighborhood Clea…
Jun 1 @ 9:00 am – 12:00 pm
Every month volunteers gather to collect garbage and help beautify our neighborhood. On average, we collect about 15 bags of garbage per clean up, which means 1,000’s of small pieces of plastic that do not[…]
Jun
4
Tue
6:30 pm West Seattle Bike Connections mo… @ Online
West Seattle Bike Connections mo… @ Online
Jun 4 @ 6:30 pm – 8:00 pm
 ShareMastodonTwitterFacebookRedditEmail
7:30 pm NW Greenways Meeting @ Virtual via Zoom
NW Greenways Meeting @ Virtual via Zoom
Jun 4 @ 7:30 pm – 8:30 pm
Our regularly scheduled meeting, happens every other month. Please check NW Greenways Twitter account – https://twitter.com/NWGreenways, our Google Group – https://goo.gl/W9jmzW or our Facebook page (https://www.facebook.com/NWGreenways/) to confirm the meeting. ShareMastodonTwitterFacebookRedditEmail
Jun
5
Wed
6:00 pm Seattle Bicycle Advisory Board M…
Seattle Bicycle Advisory Board M…
Jun 5 @ 6:00 pm – 8:00 pm
Monthly agendas can be found at: http://www.seattle.gov/seattle-bicycle-advisory-board/meetings/meeting-agendas The Seattle Bicycle Advisory Board (SBAB) advises the Mayor, City Council, and City Departments and Divisions on projects, policies, and programs that improve and/or affect bicycling conditions in[…]
— Advertisements —

Latest on Mastodon

Loading Mastodon feed…